Project Information

Address:
110 UNIVERSITY CIR.
Pueblo, CO 81005

Permit: 2203870

Workclass: 325 New Public School

Contractor:
NUNN CONSTRUCTION INC.

Planreview: 2170548   Routing #: 21-03755
Issuance Date: 2022-03-09   Permit Status: Has Final
Workdone:
NEW COMMERCIAL 16560377







Notes:
NEW SUNSET PARK SCHOOL - STATE O.P.S.
Inspections
Date Inspector Inspection Result Comments Service
2022-04-11 10:29:00   JDP   B01 - FOOTING Partial contractor is going to use 3rd party
2022-04-14 10:08:00   JDP   B16 - INSULATION Partial foundation insolation in gym area.
2022-04-19 09:11:00   JDP   B10 - PERIMETER DRAIN Partial walls around stage area
2022-04-29 10:15:00   CBC   B10 - PERIMETER DRAIN Partial interior wall drain in section-A ok.
2022-07-27 15:02:00   RDK   B04 - Frame Partial exterior wall framing marked on A101A dated 7-27-22 exterior wall framing line A3 AD THRU AF AF LINE. LINE A4 AF THRU AG, AG LINE AG THRU A7. LINE AE A9 THRU C9
2022-08-04 15:36:00   CBC   B04 - Frame Partial exterior wall framing: at grid-line AH/A9 THRU grid-line AJ/A12 of bldg-A OK.
2022-08-30 11:38:00   CBC   B04 - Frame Partial ok on building -A exterior walls and insulation at grid line A-1, A-B, A-D, A-5 ok. Roofing of building-A westside and northside ok.
2022-08-30 11:38:00   CBC   B16 - Insulation Partial ok on building-A exterior wall insulation at grid lines A-1, A-B, A-d, A-5.
2022-09-01 15:33:00   RDK   I01- Information Complete had discussion with Nunn on procedures and requirements for T.C.O.
2022-09-13 11:00:00   DDK   B04 - Frame Partial Bldg. A, interior framing preliminary. Need remaining backing and all MEP rough-ins. Seal all penetrations.
2022-09-22 10:26:00   DDK   B04 - Frame Partial South side of building A wall framing ok pending electrical rough-in. Drawing A101A
2022-10-03 09:53:00   DDK   B04 - Frame Partial Sheet A101C, Building C exterior wall framing ok except for CM to CN along C9.
2022-10-24 11:41:00   RLO   B04 - Frame Partial External fire rating/penetrations sealed, interior walls section framing ok to proceed, pending HVAC, plumbing and electrical rough sign off's. External walls interior smoke seal w/Hilti and spray foam sealed. Partial for this section ok. Waiting on Other sign-off's as listed, Section A-102 B.
2022-11-03 11:26:00   CBC   B16 - Insulation Partial Exterior wall insulation on bldg C ok.
2022-11-11 14:45:00   CBC   B04 - Frame Partial Interior wall framing: grid line CG.1 thru C1.1 from gridline CA thru CD ok.
2022-11-28 10:20:00   CBC   B04 - Frame Partial Interior nonbearing framed walls at: gridlines C7 to C9 from CB to C1 ok.
2022-12-29 10:12:00   DDK   B04 - Frame Partial Area A- gym/stage soffit and office walls ok. Area B- radius soffit framing ok.
2023-05-26 01:45:00   RDK   B06 - Building Final Rejected need 3rd party inspections. need guardrails in place at exterior stairs and handrail. need cover electrical box in for dryer. these items need to be complete for t.c.o.
2023-05-31 00:00:00   RDA   T.O. Exp. 1/1/2024 Complete - phase 1 building final of interior of building ok. exterior - of building is ok except for accessible egress routs. ok to - issue T.O. for 7 months. notes for T.O. is need final of all - phase 2 and accessible rout of phase 1 complete for C.O.
2023-05-31 12:55:00   RDK   B06 - Building Final Partial phase 1 building final of interior of building ok. exterior of building is ok except for accessible egress routs. ok to issue T.O. for 7 months. notes for T.O. is need final of all phase 2 and accessible rout of phase 1 complete for C.O.
2023-08-14 11:16:00   RDK   B06 - Building Final Partial Partial all ok for new building except for ramp curb at exterior of building. all site work is being fenced of from the new school. T.O. is ok for students in new school.
2023-08-15 02:37:00   RDK   B06 - Building Final Partial third party inspections done.
2023-10-02 10:09:00   RDK   B10 - Perimeter Drain Complete
2023-10-02 10:10:00   RDK   B10 - Perimeter Drain Complete
2023-10-13 10:31:00   RDK   B06 - Building Final Final


Permit Status
Final - Permit has received a Final.
Active - Permit does not currently have any issues.
Flagged - Permit has issues and that must be resolved.
Void - Permit has been voided. Record is still viewable but no actions can be taken.
Expired - Permit is considered expired if it has been over 180 days since last inspection.
Inspection Status
Final - Project has been completed to current code requirements and no further inspection is needed.
Complete - Inspection has passed code requirements and can proceed to the next step.
Partial - Inspection has met sufficient requirements for work to proceed with a follow up to address any issues.
No Final Given - Please review inspection notes.
Rejected - Inspection has failed to meet code requirements, review notes for required corrections.

New Search

 

Office Hours: Monday-Friday 7:30 AM to 4:30 PM
Closed Holidays:Thanksgiving + Friday after, Christmas Eve, Christmas Day, New Years Day, Memorial Day, July 4th, Labor Day
Privacy Policy | Contact Us | © 2026 Pueblo Regional Building Dept.